Client
Project Value
Location
Key Highlights
- Provision of over 600,000 m3 of imported soil fill. Average between 75,000 m3 and 150,000 m3 per month.
- Relocation of an additional 300,000 m3 of material that impeded the construction of new runways.
- Erosion control methods including silt fencing, erosion control blankets, check dams, mud mats and geo-grid.
- Maintained a safe & efficient site while following the stringent regulations of both federal (site is federally licensed) and provincial governments / authorities.