Key Highlights
- Site preparation activities included temporary silt fencing, fish removal, clearing & grubbing, cofferdams and by-pass pumping.
- Extensive traffic control plan implemented since the site is located in an area with high vehicular and pedestrian traffic.
- Reconstructed and repaired sections of culvert including:
- Removal of existing beveled ends of CSP culvert and existing culvert foundation;
- Installation of new galvanized corrugated steel bevelled culvert ends;
- Cut, chip, remove and dispose of loose and unsound concrete;
- Removal of 150mm strip of existing culvert floor;
- Repair corroded CSP culvert surface;
- Form, reinforce and pour new reinforced concrete foundation and slab;
- Repair and patch corroded steel culvert;
- Repair, patch and extend existing concrete storm sewer outlet;
- Repair and replace storm sewer pipe and catchbasin leads;
- Repair steel beam guide rail and end treatment;
- Supply and install vegetated crib wall with both structure material and bioengineering material; and
- Supply and install of native material and topsoil for slope restoration.
- Supply, place, grade and compaction of granular A, granular B and granite stone.
Other Culvert Projects
Replacement of existing open f...
Removal and disposal of existi...
Removal and disposal of existi...
Site preparation activities in...
Removal and disposal of existi...
Implemented water diversion co...